On Friday, July 12, 2024, workers will begin grinding on G Avenue from 6th Street heading to 10th Street.
On Monday, July 15, workers will grind F Avenue from 6th Street heading to 10th Street.
On Wednesday, July 17, sub-base stabilization will begin.
Our plan is to have both F and G avenues ready to re-open on Wednesday, July 31. Please know that all of this work is contingent on weather conditions allowing it to happen on schedule and that no other problems arise.
Alleyways will be rocked and remain open until paving is started.