The work on K Avenue between Sixth and Seventh streets is now in full swing. On Track is on site doing underground utility work. A significant task since starting in this area is the need to relocate a utility line. On Track will be working in this block and the adjacent alleys for the next 3-4 weeks. After that, the paving process, which is estimated at around 8 weeks, will start on K Avenue and the alleys east of Sixth Street.
West of Sixth Street on K Avenue and the adjacent alleys, paving of the mainline is completed and the “hand work” on the parking areas and sidewalks is beginning. Partial alley paving work has been accomplished and will continue.
At this point in time, the best “estimate” of when Lincoln Highway will be closed for work between 5th and 7th Streets and on Sixth Street from Lincoln Highway to M Avenue, is early August.