Nevada Central Business District (CBD) Infrastructure Improvements Project

Below is the illustration showing the proposed Phasing Map for the Nevada CBD Project. Please note this phasing is somewhat fluid and may change going forward. For instance, Phases 2 and 3 may be flipped due to the need to get underground work (sewer and water services) in place in the street prior to closing the alleys. There are water mains in all right-of-ways, including the alleys. In this project, water main will only be constructed in the street right-of-ways. Along 6th Street and the side streets, some buildings are served from the street side mains and others from the alleys. While we’ve made a great effort to identify water and sewer service locations, there are still some that unknown. Only digging will tell for sure.
Phasing Map of CBD Project (PDF)

Notice to Bidders (PDF)
Addendum to Bidder Information (PDF)
Public Meeting Information (PDF)

The proposed project consists of reconstruction of street, sidewalks, water main, sanitary sewer, storm sewer, streetscaping and street lighting will be completed for the following locations:

• 6th Street, from I Avenue to M Avenue
• J Avenue, from 5th Street to 7th Street
• K Avenue from 5th Street to 7th Street
• Lincoln Highway from 5th Street to 7th Street

The project also consists of water main replacement on 6th Street from M Avenue to N Avenue

Reconstruction of alley pavement, water main and storm sewer will occur in the North-South alleys from J Avenue to Lincoln Highway between 5th and 6th Streets and also between 6th and 7th Streets.

The project consists of the following schedule:
• Final Design (Complete by January 2020)
• Letting Phase (January 2020-February 2020): Notice to contractors of project, bidding and award of contract for construction.
• Construction Phase (April 2020-November 2021)

The estimated cost of the project is $9.0M and is being locally funded.

HR Green, Inc. is completing the design of the project. City staff will provide construction observation services for the project, with assistance from HR Green.