The second part of Street Improvement work in Nevada this season will begin this coming Monday, May 23, on North 11th Street from U Avenue to W Avenue.
Manatts will close the road, and the first order of business will be laying culvert pipe. After the pipe is completed, they will work on processes leading up to the paving of the street.
Manatts hopes to have this project completed and re-open the street no later than Monday, June 6.
{IF, after laying the culvert pipe, weather conditions prevent workers from immediately starting the processes of paving work, they might open the street for a short time until the weather is conducive to the work needing to be done.}
We thank the public for your patience as we embark on this project.